The Lift Enhancement Programme (LEP), which began in 2018, aims to upgrade the features in older lifts to meet the standards of newer ones. Supported by the Housing Development Board (HDB), the LEP was launched as part of ensuring that lifts in public housing estates comply with the standards set out by the Building and Construction Authority (BCA).

Lifts that have been in operation for 18 years and under (as of the date of commencement of the LEP), would be eligible for the LEP. The LEP is performed over a period of approximately three weeks (per lift).
Anchorvale

No LEP scheduled for 2026.

Buangkok

No LEP scheduled for 2026.

Compassvale

No LEP scheduled for 2026.

Rivervale
Block No. Street Name Lift Undergoing Maintenance Commencement of LEP Expected Date of Service Resumption
178C
Rivervale Crescent
Lift B
30 March 2026
23 April 2026
178B
Rivervale Crescent
Lift B
30 March 2026
23 April 2026
178D
Rivervale Crescent
Lift B
06 April 2026
29 April 2026
178A
Rivervale Crescent
Lift B
06 April 2026
29 April 2026
180A
Rivervale Crescent
Lift B
13 April 2026
07 May 2026
180B
Rivervale Crescent
Lift B
13 April 2026
07 May 2026
180C
Rivervale Crescent
Lift B
20 April 2026
14 May 2026
180D
Rivervale Crescent
Lift B
20 April 2026
14 May 2026
178C
Rivervale Crescent
Lift A
27 April 2026
21 May 2026
178B
Rivervale Crescent
Lift A
27 April 2026
21 May 2026
178D
Rivervale Crescent
Lift A
04 May 2026
26 May 2026
178A
Rivervale Crescent
Lift A
04 May 2026
26 May 2026
180A
Rivervale Crescent
Lift A
11 May 2026
04 June 2026
180B
Rivervale Crescent
Lift A
11 May 2026
04 June 2026
180C
Rivervale Crescent
Lift A
18 May 2026
12 June 2026
180D
Rivervale Crescent
Lift A
18 May 2026
12 June 2026
178B
Rivervale Crescent
Lift C
25 May 2026
19 June 2026